A RAILWAY line through central Glasgow will close for eight weeks to allow for improvement works.

Network Rail announced today that Glasgow’s Argyle line will close from mid-March to deliver a £32m programme of work to "improve reliability for passengers".

Customers are being urged to plan ahead as the line will be closed between Rutherglen and Exhibition Centre from March 13 to May 8.

During the closure, engineers will complete a series of projects to repair and replace tracks, tunnels and bridges on the line through Glasgow city centre.

READ MORE: Overnight closure scheduled for section of Glasgow motorway next week

Work to modernise Anderston station and install a new lift shaft will also begin, with upgrades to the booking office, concourse and platform stairs taking place.

The firm said any services via Glasgow Central Low Level, will be diverted into Glasgow Central High Level or Glasgow Queen Street Low Level.

Services will be revised and journey times may be extended to allow for trains taking a diverted route.

Glasgow Times: The Argyle line in Central Glasgow will shut for eight weeksThe Argyle line in Central Glasgow will shut for eight weeks

Replacement bus services will also be running from Carmyle, Newton, Cambuslang, Rutherglen, Dalmarnock, Bridgeton, Glasgow Central, Exhibition Centre, and Partick.

Alan Ross, Network Rail Scotland’s director of engineering and asset management, said: “This major investment in our railway infrastructure is designed to keep the line operating reliably for our customers.

“While we appreciate that some journeys will be impacted during the line closure, our work will mean that disruption and delays will be less likely in the future. And at Anderston, starting work on a new lift will make the station more easily accessible in the future.

“Such a large programme of engineering work cannot be completed without closing the line, but our teams will be working hard to finish this project as quickly as possible.

“We’re urging passengers to plan ahead when travelling during our works, whether they’re commuting to or from work, travelling to watch football or attending an event at the Scottish Event Campus (SEC).

“We’d like to thank all passengers and lineside neighbours for their patience and understanding while we carry out this essential work.”

READ MORE: Funding approved for new 'household name' supermarket in Castlemilk

David Simpson, ScotRail operations director, said: “The enhancements to the track and tunnels will improve punctuality and reliability on the route for years to come.

“Journeys will be impacted during the line closure, but once this essential work is carried out, disruption and delays will be less likely in the future.

“It’s all part of our ongoing commitment to deliver a modern, reliable, efficient, green and clean rail network as we move forward.”

Rail replacement services at affected stations will run every 30 minutes on Monday to Saturday and every hour on Sundays.

Services from Lanark, Shotts and Motherwell to Cumbernauld will operate as normal with half the normal service levels at other stations on the Argyle line outside of the closure zone.

What are the station affected in the Argyle line works?

The line will be closed between Rutherglen and Exhibition Centre. 

This means Dalmarnock, Bridgeton, Argyle Street, Glasgow Central Low Level and Anderston will also be affected.