The cost of the long running repairs to the Woodside Viaduct has increased again, the Transport Secretary has said.
Stephen Flynn told the Scottish Parliament the cost of the work is now expected to be between £175million and £185m.
Work at the viaducts which carry the M8 over Cowcaddens to the north of the city centre has been ongoing since 2021, originally planned to be complete by 2023 with an estimated cost of £81m.
Read more
Campaigners tell of successful fight to save iconic Glasgow heritage venue
New Clyde Metro report but does anyone know what it is and when it will arrive?
Ricky Bell admits city centre issues and pledges cash for safety and cleanliness
Glasgow city centre car parks to be free every weekend in December
Stephen Flynn to unveil plans to bring bus services back into public control
In response to a question by Pauline McNeill, Glasgow Labour MSP, Flynn revealed the latest estimated showing costs have more than doubled.
McNeill asked for an update on the progress of the M8 Woodside eastbound viaduct.
Flynn said: “Extensive and essential concrete repairs are required to joints.” And added it was anticipated the eastbound carriageway will reopen in early 2027 and the westbound in the second half of next year.”
He added: “It is opportune that I update the Parliament that we expect the costs of the completed project to be in the region of £175 million to £185 million.”
McNeill said: “I hope that the cabinet secretary shares my disappointment, because the road was supposed to be opened in autumn 2026 after five years of work. I was not aware, but I now know, that the road will be opened in the early part of 2027.”
She asked for better engagement with residents and business from Transport Scotland.
She added: “It is about time that we had more up-to-date information on when the road will be complete.”
(Image: Transport Scotland)
Flynn added that he like McNeill had been to see the work from the compound underneath the bridges and noted the complexities of the project.
He added: “She will be cognisant of the issues that relate to the existence of a sewer in a place that was not anticipated, the proximity of the Strathclyde Partnership for Transport subway and the need to ensure that that remains safe, and the procurement challenges that undoubtedly exist because of global matters.”
The work is not the end of the story as Transport Scotland are consulting on a permanent solution to the viaducts.
(Image: Transport Scotland)
The three options are to repair the bridges, demolish and rebuild or demolish and stop the Motorway either side of the viaducts withs costs between £125m to demolish and £500m to rebuild.
Share